At the beginning of 2011, TOTAL Congo has entrusted us with the preparation of the shutdown of its On & Offshore facilities for a period of 3 years:
Among these shutdowns, the most important was the N'KOSSA shutdown in early 2013. Volume of the shutdown: 865 operators maximum day and night, 420,000 hours of work completed in 60 days.
During 24 months, our team carried out the detailed preparation of the technical specifications for the call for tenders and the management of spare parts.
2909 Requests for Intervention were processed by our team of 4 preparers over 24 months, 20,000 hours of work to successfully complete this mission for which we will receive the congratulations of our client TOTAL.
92 capacity interventions.
291 pipework interventions.
894 interventions Valves (HV-VA-VM-CL-PSV).
156 Instrumentation interventions.
And numerous interventions in new works (DPTN); electricity; mechanics; insulation; painting; wells...
Head office
Immeuble Le Montréal
18 rue Amiral Cécille
76100 Rouen
+33 (2) 35 73 39 19
Contact us
© ALPHA MAINTENANCE - Subsidiary of Ponticelli Group